Installation Procedure
- Install the generator cable (2) to the junction block.
- Install the generator cable nut.
Tighten: Tighten the nut to 9 N.m (80 lb in).
- Close the positive cable junction block.
- Install the generator cable to the generator, perform the following:
- Install the generator cable to the stud.
- Install the generator cable nut.
Tighten: Tighten the nut to 9 N.m (80 lb in).
- Position the boot to cover the stud.
- Connect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection .
NOTE:
Use the correct fastener in the correct location. Replacement fasteners must be the correct part number for that application. Fasteners requiring replacement or fasteners requiring the use of thread locking compound or sealant are identified in the service procedure. Do not use paints, lubricants, or corrosion inhibitors on fasteners or fastener joint surfaces unless specified. These coatings affect fastener torque and joint clamping force and may damage the fastener. Use the correct tightening sequence and specifications when installing fasteners in order to avoid damage to parts and systems.