lemon-mirror:
Home >> Jeep >> 2003 >> Grand Cherokee Overland >> Repair and Diagnosis >> Electrical >> Starter >> Starting System >> System Testing >> Feed Circuit Test

Feed Circuit Test

The starter feed circuit test (voltage drop method) will determine if there is excessive resistance in the high-amperage feed circuit. For complete circuit diagrams, see WIRING DIAGRAMS  .

When performing these tests, it is important to remember that the voltage drop is giving an indication of the resistance between the two points at which the voltmeter probes are attached.

Example:  When testing the resistance of the battery positive cable, touch the voltmeter leads to the battery positive cable clamp and the cable connector at the starter solenoid. If you probe the battery positive terminal post and the cable connector at the starter solenoid, you are reading the combined voltage drop in the battery positive cable clamp-to-terminal post connection and the battery positive cable.

The following operation will require a voltmeter accurate to 1/10 (0.10) volt. Before performing the tests, be certain that the following procedures are accomplished:

  1. Connect the positive lead of the voltmeter to the battery negative terminal post. Connect the negative lead of the voltmeter to the battery negative cable clamp. See Fig 1 . Rotate and hold the ignition switch in the Start position. Observe the voltmeter. If voltage is detected, correct the poor contact between the cable clamp and the terminal post.
    Fig 1: Test Battery Negative Connection Resistance
    G00309757Courtesy of DAIMLERCHRYSLER CORP.
  2. Connect the positive lead of the voltmeter to the battery positive terminal post. Connect the negative lead of the voltmeter to the battery positive cable clamp. See Fig 2 . Rotate and hold the ignition switch in the Start position. Observe the voltmeter. If voltage is detected, correct the poor contact between the cable clamp and the terminal post.
    Fig 2: Test Battery Positive Connection Resistance
    G00309761Courtesy of DAIMLERCHRYSLER CORP.
  3. Connect the voltmeter to measure between the battery positive terminal post and the starter solenoid battery terminal stud. See Fig 3 . Rotate and hold the ignition switch in the Start position. Observe the voltmeter. If the reading is above 0.2 volt, clean and tighten the battery cable connection at the solenoid.

    Repeat the test. If the reading is still above 0.2 volt, replace the faulty battery positive cable.

    Fig 3: Test Battery Positive Cable Resistance
    G00312507Courtesy of DAIMLERCHRYSLER CORP.
  4. Connect the voltmeter to measure between the battery negative terminal post and a good clean ground on the engine block. See Fig 4 . Rotate and hold the ignition switch in the Start position. Observe the voltmeter. If the reading is above 0.2 volt, clean and tighten the battery negative cable attachment on the engine block. Repeat the test. If the reading is still above 0.2 volt, replace the faulty battery negative cable.
    Fig 4: Test Ground Circuit
    G00312511Courtesy of DAIMLERCHRYSLER CORP.
  5. Connect the positive lead of the voltmeter to the starter housing. Connect the negative lead of the voltmeter to the battery negative terminal post. See Fig 5 . Rotate and hold the ignition switch in the Start position. Observe the voltmeter. If the reading is above 0.2 volt, correct the poor starter to engine block ground contact.
    Fig 5: Test Starter Ground
    G00312515Courtesy of DAIMLERCHRYSLER CORP.

If the resistance tests detect no feed circuit problems, refer to STARTER MOTOR  underCOMPONENT TESTING.