Charging System (Service Information): Generator: Installation: Installation
Courtesy of CHRYSLER GROUP, LLC
- Install the generator (1).
Courtesy of CHRYSLER GROUP, LLC
- Install the lower bolt finger tight.
Courtesy of CHRYSLER GROUP, LLC
- Install the upper generator mounting bolt. Tighten upper and lower bolts to 54 N.m (40 ft. lbs.).
Courtesy of CHRYSLER GROUP, LLC
- Install the B+ cable. Tighten nut to 10 N.m (89 in. lbs.).
Courtesy of CHRYSLER GROUP, LLC
- Connect the generator field wire harness connector.
Courtesy of CHRYSLER GROUP, LLC
- Install the A/C compressor. Refer to COMPRESSOR, A/C, INSTALLATION
.
Courtesy of CHRYSLER GROUP, LLC
- Install the accessory drive idler pulley.
- Install the serpentine belt (3). Refer to BELT, SERPENTINE, INSTALLATION
.
Courtesy of CHRYSLER GROUP, LLC
- Install the accessory drive splash shield.
- Install the underbody air dam.
- Install the right front wheel.
- Evacuate and fill the A/C System. Refer to PLUMBING, STANDARD PROCEDURE
.
- Connect the negative battery cable.
Courtesy of CHRYSLER GROUP, LLC
- Install the air inlet tube. Fasten with two screws (3).