Light Control Rheostat: Installation
- INSTALL LIGHT CONTROL RHEOSTAT
- Engage the 2 claws to install the light control rheostat.
- INSTALL NO. 1 SWITCH HOLE BASE (See INSTALLATION ).
- INSTALL UPPER INSTRUMENT PANEL SUB-ASSEMBLY (See INSTALLATION ).
- INSTALL GLOVE COMPARTMENT DOOR ASSEMBLY (See INSTALLATION ).
- INSTALL COMBINATION METER ASSEMBLY (See INSTALLATION )
- INSTALL INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY (See INSTALLATION ).
- INSTALL INSTRUMENT CLUSTER FINISH LOWER PANEL (See INSTALLATION ).
- INSTALL INSTRUMENT CLUSTER FINISH CENTER PANEL SUB-ASSEMBLY (See INSTALLATION ).
- INSTALL FRONT PILLAR GARNISH LH (See INSTALLATION ).
- INSTALL FRONT PILLAR GARNISH RH (See INSTALLATION ).
- INSTALL FRONT DOOR OPENING TRIM WEATHERSTRIP LH (See INSTALLATION ).
- INSTALL FRONT DOOR OPENING TRIM WEATHERSTRIP RH (See INSTALLATION ).
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
Torque: 5.4 N*m (55 kgf*cm, 48 in.*lbf)