Charging System (Service Information): Generator: Installation: Installation
- INSTALL GENERATOR ASSEMBLY
- Install the generator with the 2 bolts.
Torque: 52 N*m (530 kgf*cm, 38 ft.*lbf)
- Install the wire harness clamp bracket with the bolt.
Torque: 8.4 N*m (85 kgf*cm, 74 in.*lbf)
- Connect the generator wire with the nut.
Torque: 9.8 N*m (100 kgf*cm, 87 in.*lbf)
- Install the terminal cap.
- Connect the generator connector.
- Install the generator with the 2 bolts.
- INSTALL WIRE HARNESS CLAMP BRACKET
- Install the clamp bracket with the bolt.
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
- Attach the wire harness clamp to the clamp bracket.
- Install the clamp bracket with the bolt.
- INSTALL FAN AND GENERATOR V BELT
Refer to INSTALLATION
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL NOTE: When disconnecting the cable, some systems need to be initialized after the cable is reconnected. Refer to INITIALIZATION .