Circuit Opening Relay: Inspection
- REMOVE RELAY BOX COVER
- REMOVE CIRCUIT OPENING RELAY (Marking: C/O)
- INSPECT CIRCUIT OPENING RELAY CONTINUITY
- Using an ohmmeter, check that there is continuity between terminals 1 and 2.
If there is no continuity, replace the relay.
- Check that there is no continuity between terminals 3 and 5.
If there is continuity, replace the relay.
- Using an ohmmeter, check that there is continuity between terminals 1 and 2.
- INSPECT CIRCUIT OPENING RELAY OPERATION
- Apply battery positive voltage across terminals 1 and 2.
- Using an ohmmeter, check that there is continuity between terminals 3 and 5.
If there is no continuity, replace the relay.
- REINSTALL CIRCUIT OPENING RELAY
- REINSTALL RELAY BOX COVER