Throttle Body: Installation
- INSTALL THROTTLE WITH MOTOR BODY ASSEMBLY
- Install a new gasket and the throttle with motor body with the 4 bolts.
Torque: 11 N*m (112 kgf*cm, 9 ft.*lbf)
- Connect the throttle motor connector.
- Connect the water by-pass hose No. 4.
- Connect the water by-pass hose No. 5.
- Install a new gasket and the throttle with motor body with the 4 bolts.
- INSTALL AIR CLEANER ASSEMBLY
- Install the air cleaner with the 2 bolts.
Torque: 8.0 N*m (82 kgf*cm, 71 in.*lbf)
- Connect the ventilation hose No. 2.
- Install the air cleaner with the 2 bolts.
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
Torque: 3.9 N*m (40 kgf*cm, 35 in.*lbf)
- ADD ENGINE COOLANT (See REPLACEMENT )
- CHECK FOR ENGINE COOLANT LEAKAGE (See REPLACEMENT )
- INSTALL V-BANK COVER
- Install the V-bank cover with the 2 nuts.
Torque: 7.5 N*m (76 kgf*cm, 66 in.*lbf)
- Install the V-bank cover with the 2 nuts.